There has been a recent upsurge in interest in the Acoustic Fish Deterrent after a consultation was launched by EDF to remove the necessary environmental protection.
This mini-site provides information on the system, and it's need at Hinkley Point C. The article below is an example of this interest.
“Fish Guidance Systems is unimpressed at EDF’s change of direction, saying it was like building wind turbines that would kill millions of birds and offering to build a nature reserve next door.”
Acoustic Fish Deterrents at Hinkley Point C
A Necessary Environmental Protection
Hinkley Point C is the first of a new generation of nuclear power stations in the UK. The plant is due to open in June 2031 and will cost up to £46bn. Hinkley Point C will account for 7% of the country’s electricity supply, providing power to around six million homes and offsetting nine million tonnes of carbon dioxide each year.
All current plans at Hinkley Point C include an AFD to prevent fish from being drawn into the extensive cooling facilities. The water will be drawn from the Severn Estuary—a designated special area of conservation. The necessary Acoustic Fish Deterrent (AFD) must be installed to prevent 182 million fish per year from being killed, this figure is part of a Welsh Government report on the AFD.
The AFD will guide fish away from the plant’s water intakes to protect them from harm. EDF is currently planning to remove this necessary environmental protection because of unfounded concerns about noise, access, and cost, all of which are addressed below.
- Prof Mark Everard Discusses AFD on BBC Radio 4Dr. Mark Everard, Associate Professor of Ecosystem Services at the University of the West of England, took to BBC Radio 4’s Farming Today on Monday 25th November 2024, to advocate for the installation of an Acoustic Fish Deterrent (AFD) at Hinkley Point C. The interview, which can be found on… Read more: Prof Mark Everard Discusses AFD on BBC Radio 4
- How the AFD Delivery Report Changes the Conversation at Hinkley Point CThe conversation around the Acoustic Fish Deterrent (AFD) at Hinkley Point C has drastically changed after the AFD Delivery Group released a report that answered and overcame the challenges facing EDF regarding the available technologies and maintenance of the system. The AFD, which is government mandated, UK best practice, and… Read more: How the AFD Delivery Report Changes the Conversation at Hinkley Point C
- Nuclear power plant constructors undermine environmental protection measuresIn an open NNB Generation Company (HPC) Limited letter that explores changes toMaisemore Weir as an alternative to the already approved Acoustic Fish Deterrent (AFD) at HinkleyPoint C, the company flagrantly disregards and negates the proven science and technology which wouldprevent catastrophic environmental implications such as the death of 182… Read more: Nuclear power plant constructors undermine environmental protection measures
- Moved Saltmarsh Won’t Save 182 million Fish Per Year: The Best Solution Remains The Acoustic Fish DeterrentAfter the public consultation back in January, EDF is now looking at alternative and less desirable saltmarsh locations after public rejection from residents, environmentalists, and a report from the Environment Agency. The answer to the problem continues to be the Acoustic Fish Deterrent. Video regarding Salt Marshes The saltmarsh, while… Read more: Moved Saltmarsh Won’t Save 182 million Fish Per Year: The Best Solution Remains The Acoustic Fish Deterrent
- Overview of the Environment Agency’s Response to EDF’s Plans to Remove AFD from Hinkley Point CIn early June, The Environment Agency provided a response to the Hinkley Point C Development Consent Order Material Change consultation. The Environment Agency mission is to ensure that Hinkley Point C (HPC) operates to high environmental standards and states that it will continue to engage with EDF to achieve this.… Read more: Overview of the Environment Agency’s Response to EDF’s Plans to Remove AFD from Hinkley Point C
Hinkley Point C and the Acoustic Fish Deterrent
For over a decade EDF have been attempting to remove the Acoustic Fish Deterrent, a necessary environmental protection, from Hinkley Point C, an act that would kill 182 million fish per year for the next sixty years. In this time, Fish Guidance Systems have been working towards the installation of an Acoustic Fish Deterrent at Hinkley Point C through innovation, education and positive engagement.
During this time, we have been committed to working with EDF to deliver this necessary and important environmental protection. Despite this, there have been many attempts to remove the AFD, independent organisations, including the UK and Welsh Government, have stated the technology must be installed.
There has been a growing interest in the Acoustic Fish Deterrent (AFD) after a new consultation was launched by EDF to remove this necessary environmental protection.
This mini-site provides information on the system and its necessity at Hinkley Point C. In addition, we have provided links to articles, reports and independent assessments to show the public support for the AFD.
“Fish Guidance Systems is unimpressed at EDF’s change of direction, saying it was like building wind turbines that would kill millions of birds and offering to build a nature reserve next door.”
Click here to read the full Guardian article.
- Prof Mark Everard Discusses AFD on BBC Radio 4Dr. Mark Everard, Associate Professor of Ecosystem Services at the University of the West of England, took to BBC Radio 4’s Farming Today on Monday 25th November 2024, to advocate for the installation of an Acoustic Fish Deterrent (AFD) at Hinkley Point C. The interview, which can be found on… Read more: Prof Mark Everard Discusses AFD on BBC Radio 4
- How the AFD Delivery Report Changes the Conversation at Hinkley Point CThe conversation around the Acoustic Fish Deterrent (AFD) at Hinkley Point C has drastically changed after the AFD Delivery Group released a report that answered and overcame the challenges facing EDF regarding the available technologies and maintenance of the system. The AFD, which is government mandated, UK best practice, and… Read more: How the AFD Delivery Report Changes the Conversation at Hinkley Point C
- Nuclear power plant constructors undermine environmental protection measuresIn an open NNB Generation Company (HPC) Limited letter that explores changes toMaisemore Weir as an alternative to the already approved Acoustic Fish Deterrent (AFD) at HinkleyPoint C, the company flagrantly disregards and negates the proven science and technology which wouldprevent catastrophic environmental implications such as the death of 182… Read more: Nuclear power plant constructors undermine environmental protection measures
- Moved Saltmarsh Won’t Save 182 million Fish Per Year: The Best Solution Remains The Acoustic Fish DeterrentAfter the public consultation back in January, EDF is now looking at alternative and less desirable saltmarsh locations after public rejection from residents, environmentalists, and a report from the Environment Agency. The answer to the problem continues to be the Acoustic Fish Deterrent. Video regarding Salt Marshes The saltmarsh, while… Read more: Moved Saltmarsh Won’t Save 182 million Fish Per Year: The Best Solution Remains The Acoustic Fish Deterrent
- Overview of the Environment Agency’s Response to EDF’s Plans to Remove AFD from Hinkley Point CIn early June, The Environment Agency provided a response to the Hinkley Point C Development Consent Order Material Change consultation. The Environment Agency mission is to ensure that Hinkley Point C (HPC) operates to high environmental standards and states that it will continue to engage with EDF to achieve this.… Read more: Overview of the Environment Agency’s Response to EDF’s Plans to Remove AFD from Hinkley Point C
'Final' decision already made by government to install AFD
In September 2022, an appeal to remove the AFD from the plant by EDF was rejected by the Department of Business, Energy and Industrial Strategy. This was the last recourse for EDF, except for a judicial review. However, a new public inquiry is now being rumoured due to a technical change in approach.
In their report, which can be found here, they stated:
“The Secretary of State considers that the migratory species have been declining, are considered in a poor state and that even low-level impacts on a population at risk can be significant. He also considers that the marine stocks are in a poor or vulnerable state and that impacts of the scale indicated by the… [removal of the AFD] would have a potential material effect on these stocks.”
Environmental Permitting Regulations 2016 Appeal by NNB Generating Company (HPC) Ltd Removal of acoustic fish deterrent conditions from Water Discharge Activity (WDA) Permit
The quick facts on AFD claims
In January 2024, a consultation on the idea of replacing the AFD with a salt-marsh as been widely rejected by the public and environmental organisations. As part of the consultation, EDF claimed incorrectly several aspects of the AFD. These are the clarifications:
- The AFD would not be heard from the shore (36.5db at 2 miles away and up to 20 metres underwater).
- An AFD was tested in Hartlepool, where local seal populations were monitored with no effect on their behaviour (AFD sounds at 1,000hz, peak range of sea mammal hearing is 20,000hz).
- The nature reserve is a worthwhile environmental addition if done right but would not stop a single one of the 182 million fish killed without the AFD from dying.
- ROV systems are developing rapidly, with improved capabilities for navigation in challenging conditions, such as very low visibility, onshore control, advanced navigation software, more ROV power, and manipulators with greater control and accuracy.
What can an Acoustic Fish Deterrent (AFD) achieve?
As part of the Development Consent Order, the AFD has been approved and reaffirmed multiple times for Hinkley Point C.
The Government, the Welsh Government, and a Public Inquiry have all stated that the AFD will play an essential role in protecting marine life and must be installed. Without it, environmental organisations believe that 182 million fish could be pulled into the intake each year.
An effective screening system comprises a fish return system with an AFD, accounting for various factors, including:
- Differences in fragility of the fish at risk.
- Differences in handling sensitivities of the fish drawn into the intake.
- The potential for fish stocks to change over the plant’s lifespan.
- A safe maintenance process that protects divers and other operatives.
The decision on the installation of the AFD had been settled. However, EDF continues its attempts to remove necessary environmental protections.
Fish Guidance Systems provided statements at the public inquiry of June 8th, 2022. Dr. David Lambert, Managing Director of Fish Guidance Systems, and Dr. Andy Turnpenny, fish biologist, gave a presentation on the AFD’s requirements to be included in the DCO for the proposed nuclear plant. To view their full statements, please follow the link below.
Thirty Years of Experience.
FGS has been developing sound-based behavioural fish protection systems for over 30 years. These are backed by scientific research and multiple trials to assess effectiveness and environmental impact.
The type proposed for Hinkley Point C uses a Sound Projector Array, a system of underwater speakers that produce a repellent sound gradient to block intakes.
Species such as Atlantic salmon and twaite shad, which are abundant in the Severn Estuary and of high conservation importance, have responded particularly well to existing AFDs.
Our Latest Acoustic Fish Deterrent News
ROV improvements and innovative thinking the key to Acoustic Fish Deterrent
Fish Guidance Systems has presented a detailed argument advocating the use of Remotely Operated Vehicles (ROVs) to address safety concerns in the maintenance of Acoustic Fish Deterrent (AFD) systems at Hinkley Point C. It has previously presented this at Environment Agency, Welsh Government and UK Government Public Inquiries, the latter two
FGS response to EDF’s Noise Claims
Fish Guidance Systems has refuted claims by EDF that its acoustic fish deterrent (AFD) would create a noise “louder than a jumbo jet” at Hinkley Point C when it comes on line. EDF has instead suggested creating a salt marsh as a “natural” alternative to installing the AFD, which would
Environment Agency Hinkley Point C Consultations Closes With Campaigners Furious At Continued Need Fight Over Environmental Protections.
As the Environment Agency’s Consultation on EDF’s latest attempt to remove the AFD mandated by best practice and expert option closes, they have have faced strong criticism for allowing EDF to continue their campaign to remove environmental protections at Hinkley Point C, a nuclear power plant being built by French
Fish Guidance Systems Seeking Clarity on Continued Permit Appeals at Hinkley Point C after Secretary of States’ Intervention
Fish Guidance Systems are disappointed to hear of proposed changes to permit conditions at Hinkley Point C nuclear power station. After participating in the public inquiry in 2022 and having received a letter from the Secretary of State for Business, Energy and Industrial Strategy stating the matter is closed, we